|
SOLAR
Background
From a
purely technical perspective, and regardless of market
considerations, Cambodia has excellent potential for
photovoltaic power generation. NEDO (2002) has produced a
solar radiation map for
Cambodia,
using data from NASA’s Langley Research Center (LaRC) and the
US National Renewable Energy Laboratory (NREL). Solar
radiation or “solar insolation” increases gradually from the
northwest of the country with an average low of 4.11 kWh/m2
to the southwest of the country with an average high of 5.23
kWh/m2. The maximum fluctuation in solar radiation
volume throughout the year is relatively low, and has been
estimated at 17%. The NEDO solar radiation map shows that all
of
Cambodia
has “extremely good potential” for photovoltaic power
generation.
The use of PV systems in Cambodia began with a few
installations donated by UNICEF, the Red Cross, La Fondation
Énergies Pour Le Monde (FONDEM), NEDO, EBARA and other NGOs.
Most of the applications were for health and rehabilitation
centres, but solar home systems (SHSs) and lighting systems
were also installed as demonstration units. Table 1 gives a
list of the PV systems installed in Cambodia according to the
different applications. To promote this technology in rural
areas, where users have a low level of technical knowledge on
PV, awareness raising, trained technicians, availability of
accessories, etc are essential. Adaptive research is also
required to reduce the high cost of PV systems, and to repair
and maintain these systems in the long run.
Project/Program
The
Government Cambodia's Renewable Electricity Action Plan
provides framework supporting small-scale generation
electricity local communities. Plan product major effort
Cambodia's Department Energy Technique design decentralized
system electricity supply based on innovative thinking latest
renewable energy technologies.
Renewable energy
technologies and off line community owned power grids are
viable alternatives. Systems using technologies that transform
locally available biomass into cheap electrical energy have
been developed and perfected. These technologies can supply
reliable and affordable electricity for irrigation water
systems, household lighting and appliances, local industry
needs and other public and private services.
-
Cambodia has not yet set up standard relating to PV
system.
-
Cambodia doe not yet produce components/PV panels for
the solar system. Also we do not yet any sophisticated
laboratory or facilities to test such a PV system or
components.
-
Under WB/ADB’s RE&T Project, we are doing the
adaptation of the international best practices, which are
recommended by these international institutions, by taking
into account our local environment.
-
In order to allow new PV system products into the
Cambodia market and in order to reduce the price, also at the
time to protect the consumers by providing them with only
reliable and well-proven equipment/technologies, these new
products must provide certification of their products,
acceptable to the WB recommendation/guidelines for example.
A Regional Research and Dissemination Programme, supported by
the Swedish International Development Cooperation Agency (Sida)
and coordinated by the Asian Institute of Technology (AIT)
was established. PV accessories were developed locally,
allowing the reduction of the system cost and making the spare
parts available within the country. Demonstration systems were
installed to allow the potential users learned about the uses
and benefits of PV systems, thus increasing awareness of the
technology. Local persons were trained on operation,
maintenance and management (OM&M) with an aim to establish
after sales service available locally. Staffs from different
organizations were trained both nationally and internationally
to carry out research and dissemination activities
effectively. Results and findings obtained from this program
were disseminated by conducting workshops/seminars as well as
articles published in conferences and workshops. For the
technology package, the Ministry of Industry, Mines and Energy
(MIME) developed the "charge controller" with automatic high
and low voltage cut-off options. They were tested in
laboratory and field to ensure its satisfactory performance.
In addition, this ensured availability of spare parts and
after-sales-service. The field technicians are able to repair
the faulty controllers locally, which yielded better
reliability of the systems to the users. The technology of
charge controllers, developed under the programme was
transferred to the Department of Energy Technique (MIME/DET),
which manufactured them using this design and installed them
in other demonstration projects (funded by the government)
such as the 1.875 kWp installations at Prek Takouch bridge and
two development centres in Pursat and Preah Vihear provinces,
and other bridges in Cambodia.
PV installations in Cambodia during 1997–2004
|
Applications |
Capacity (kWp) |
|
Lighting |
55.9 |
|
Pumping |
13.3 |
|
Refrigerator |
7.8 |
|
Computers |
6.9 |
|
Radio repeater |
1.9 |
|
Telecommunication equipment (for mobile phones) |
1,050.0 |
|
Total |
1,135.8 |
MIME has installed 200 PV systems in health centres (powers
light, pump, fan, radio telephone and refrigerator), bridges
(powers street lights) school, development centres and pagodas
(powers lights) in Cambodia. These demonstration systems allow
potential users to get a good idea of the technology and its
use. The use of PV systems in health centres also offers the
rural population more reliable medical services. As well as
using these practical, working examples, MIME developed and
distributed brochures containing information about the
technology, and published articles in national press. Seminars
and workshops were also conducted, where government personnel,
NGOs, international agencies, potential users and
entrepreneurs were all invited. Many TV programmes on the
subject of PV, including interviews with the users, and PV
experts showing the practical use of PV systems were made.
According to the World Bank review of rural electrification
experience in Asia, PV projects should be considered in the
electrification planning process to arrive at a least-cost
option; although grid electricity is preferable to users in
terms of affordability and usefulness, national economic
policy should direct a least-cost and sustainable path to
energy service delivery. Since the implementation of the ‘RETs
in Asia’ project, the Royal Government of Cambodia has shown
great interest in rural PV electrification. The Government has
established a working group to co-operate with Japan and
certain NGOs in order to encourage the renewable energy
development, especially solar, and a renewable energy
development strategy is now included in the national energy
policy. In the rural electrification action plan for ten years
developed under the Rural Electrification Fund (REF), the
Government plans to install 12,000 solar PV systems (40 Wp
each). The participation of the private sector will be
encouraged, and the scheme will subsidize all new renewable
energy installations producing electricity. A draft plan to
provide duty and tax exemptions for all imported renewable
energy equipment is also under preparation. REF will also get
funding from the national budget.
RENEWABLE ELECTRICITY ACTION PLAN
Cambodia’s Renewable Electricity Action Plan (REAP) has five
guiding principles:
-
Renewable energy technologies will be used when economically
least cost
-
The RGC will serve the role of market enabler
-
Private sector firms will serve as market developers and
suppliers
-
Decision on renewable electricity development for the needs
of the poor
-
Subsidies and credit will be used carefully
The REAP long-term targets are:
-
5% of all new installed capacity, or about 6MW of mini hydro
and 850 kW of village hydro, will be supplied by renewable
electricity technologies and delivered to rural households
or businesses.
-
50 000 new households connected by Rural Electricity
Enterprises (REE) off-grid extension;
-
12,000 households will be served by solar photovoltaic.
-
A sustainable market for renewable electricity system should
be developed.
RURAL ELECTRIFICATION FUND
A key component for implementation of the REAP is the Rural
Electrification Fund (REF) which is part of the Rural
Electrification and Transmission (RE&T) project, funded by the
World Bank and Asian Development Bank (ADB).
The REF will consist of approximately 25% of the total project
investment and implement rural electrification solutions in
particular nominated areas, consisting, for time being and in
the initial pilot phase, of either:
a. New mini-grids based on generation from diesel, solar or
hydropower generation. For diesel generation, only new
household connections are eligible for REF grants.
b. Extension of an existing small grid systems to connect new
households;
c. Solar Home Systems (SHS); or
d. Mini or Micro hydropower system.
Financing rural electrification investment projects can be a
barrier due to banks' credit conditions: short term loan, high
interest rate and large collateral. The RGC and the World Bank
Group (WBG) are working to upgrade the banking system. In this
context - and although the interest rate is still relatively
high - there is an optimistic note concerning the "success
story" of the Cambodian Micro Financing Institution, as
reported in March 2005 by the WBG's Mekong Private Sector
Development Facility.
The intended effects of the REF grant is to reduce the capital
investment cost and thus reducing the retail cost of power in
rural areas. And this, combined with an operating licence
granted by the Electricity Authority of Cambodia (EAC), will
enable the proponent to successfully obtain the remaining
finance from a private finance institution. Technical
assistance will be provided to further assist proponents to
secure appropriate debt finance.
BARRIERS
□
High initial
investment for biomass-electric power conversion technology,
□
Due
to organizational and managerial barriers and also due to the
lack of means, Cambodia cannot yet address properly the
population basic needs;
□
Lack of basic socio-economic and technical data;
□
Low
awareness due to lack of information;
□
Weakness in Financing, Banking and Credit systems.
□
To address these barriers, we need, to begin with, to
have human resources, which are both competent and motivated.
The market should be developed in order to reduce the cost,
and subsidies are must.
INSTITUTIONAL SET UP AND FINANCE
The
intended effects of the REF grant is to reduce the capital
cost and thus the retail cost of power in rural areas and
also, combined with an operating licence from the Electricity
Authority of Cambodia (EAC), to enable the proponent to
successfully obtain the remaining finance from a private
finance institution. Technical assistance will be provided to
further assist proponents to secure appropriate debt finance.
|
Project Type |
Total Cost |
REF Grant |
|
Solar Home System |
US$400
per set of 40 Wp |
US$100
per set of 40 Wp |
For PV systems to be successful, it is very important to
building institutional frameworks for their management.
Experience shows that the involvement of the local community
can help avoid problems such as non-payment, mishandling and
irregular maintenance. In Cambodia, MIME established
institutional arrangements according to local conditions. In
the province of Pursat, for instance, 20 households each in
the villages of Kandor Sar and Anlong were selected for PV
installations, including a leader from each village. These
leaders were given responsibility for taking care of the
systems installed in their villages, and were trained in
maintenance and basic troubleshooting. To enhance in-house
expertise, staff from MIME attended special courses at the
Asian Institute of Technology (AIT) and at Solar Lab in
Vietnam. These solar energy courses looked at design of
systems such as inverters, charge controllers and other PV
accessories. MIME trained 50 PV system users in efficient
operation and basic troubleshooting, reducing the need for
external maintenance. The training focused on the basic
components of SHSs, installation, maintenance, common problems
and troubleshooting procedures. Booklets containing relevant
information were distributed to the participants. The training
helped users in remote areas to perform maintenance of their
systems themselves, so they could carry out tasks such as
replacing burnt fuses and tubes, and replenishing the
battery’s supply of water when needed.
Poor economic conditions and the social inequality between
urban and rural populations, financing expensive PV systems is
a difficult and challenging task for the Royal Government of
Cambodia. PV systems used by telecommunication companies, for
instance, are technically and economically proven, because
they are financed by the companies themselves, while most of
the SHS installations have been donated by International
Organizations and NGOs, such as Sida, NEDO, Fondation reconnue
d’utilité publique (FONDEM), CDG, World Vision, so there are
few cases of actual sales with cash payment. A credit system
for household equipment (consumer items) is not yet well
developed. With the Royal Government of Cambodia and World
Bank and ADB rural Electrification and Transmission Projects,
the private sector is now expected to participate in
development, commercialisation and financing of all renewable
energy in Cambodia. Under the Rural Electrification Fund,
there will be a subsidy scheme with grants from donors and the
Global Environment Facility (GEF) designed to encourage the
use of PV systems, and mini hydro making them affordable to
the rural population. Low-interest loans will be provided to
entrepreneurs and micro-finance institutions dealing with
sales, installations and maintenance of solar systems. Table 2
shows a summary of the proposed grants.
ADAPTIVE RESEARCH
In the PV system, PV module is the main component and
batteries are imported, and the balance-of-system (BoS)
components could be developed locally. Surveys carried out in
Cambodia indicated that PV accessories such as lamps, charge
controllers and DC–DC converters were not available. The
imported items were expensive and posed various difficulties,
including lack of spare parts and no after sales service; in
most cases, any faulty devices had to be replaced with new
ones. Ministry of Industry, Mines and Energy (MIME) addressed
these issues by developing a 12V, 10A charge controller with
automatic high- and low-voltage cut-off options. These
controllers were subject to both laboratory and field tests to
ensure their satisfactory performance. The charge controller
also included an LED to indicate the status of the battery.
The charge controller technology developed under the programme
was transferred to the Department of Energy Technique (MIME/DET),
which manufactured them using this design. These were
installed in other demonstration projects (funded by the
Government), such as the 1.9 kWp installations at Prek Takouch
bridge, and two development centres in the provinces of Pursat
and Preah Vihear.
Use of these charge controllers helped to reduce the price of
PV systems, and it also ensured availability of spare parts
and after-sales service. As local field technicians are able
to repair the faulty controllers, users are more satisfied by
system reliability.
SUPPLIERS
KHMER SOLAR Co.Ltd
#71, Norodom Blvd, Phnom Penh
Cambodia
Tel: (855)23-212-212 or (855)
16-830-038
Renewable Equipment Supply, Spare Parts & Services
COMIN KHMERE Co.Ltd
#48 Samdech Pan (Str.214),
Phnom Penh Cambodia
Tel: (855)23-426-056
Generators - Supply, Rental, Spare Parts & Services
Key Players
GOVERNMENT:
Ministry of Industry, Mines
and Energy: Department of Energy Technique
PRIVATE SECORS:
1.
KHMER SOLAR Co.Ltd.
2.
METROFILE ENGINEERING
3.
COMIN KHMERE Co.Ltd
NON
GOVERNMENT ORGANIZATION:
- REPSA
(Renewable Energy Private Sector Association), from KHMER
SOLAR,
Director, Jean-Pierre
Mahé of Kosan-Gret, As Secretary General of REPSA.
- CRCD (Cambodian Research
Centre for Development)
ACADEMIC:
1. Institute Technology of
Cambodia (ITC)
DONORS, INTERNATIONAL INSTITUTIONS:
SIDA (Sweden), NEDO (Japan),
FONDEM, CDG (Invent), The World Bank Group, Asian Development
Bank
BANKS & MICRO FINANCING INSTITUTIONS (MFI):
ACLEDA, CANADIA,
|